What does fast tracking a schedule involve?

  1. Adding resources to critical path activities

  2. Increasing the budget for the project

  3. Allowing team members to work overtime

  4. Performing critical path activities simultaneously

The correct answer is: Performing critical path activities simultaneously

Fast tracking a schedule involves performing critical path activities simultaneously instead of in a sequential manner. This technique is used to accelerate the project timeline by overlapping tasks that would traditionally be done one after another. By doing so, the project team can potentially reduce the overall duration of the project, which is especially useful when a project is behind schedule or when there's a need to meet early deadlines. In the process of fast tracking, care must be taken to manage dependencies between tasks, as overlapping activities can lead to resource conflicts and increased risk. This method does not involve adding resources to activities, increasing the project's budget, or allowing team members to work overtime; instead, it focuses on optimizing the schedule by re-evaluating how tasks are organized and executed.